(Back)

Neither Snohomish County nor the Department of Planning and Development Services warrants the accuracy, reliability or timeliness of any information contained herein and shall not be held liable for losses caused by using this information. Portions of this information may not be current or accurate. Any person or entity who relies on any information obtained from this system, does so at his or her own risk. All critical information should be independently verified.

RCW 42.17.260(9) prohibits the release of lists of individuals requested for commercial purposes, and requestor expressly represents that no such use of any such list will be made by user or its transferee(s) or vendee(s). "Commercial purposes" means contacting or in some way personally affecting the individuals identified on the list with the purpose of facilitating one’s commercial activities.
Data below is from 2/22/2017 12:28:54 PM
Parcel (Tax Account) Number: 280603-001-004-00
Address: JOB LOCATION , SNOHOMISH, WA 98290
Project File Number: 04-112029-000-00-SD Current Status: Preliminary Approval
Application Date: 4/20/2004 12:00:00 AM Issue Date: 3/8/2006 12:00:00 AM
Project Type: Subdivision Type: Plat-Prelim
Information:
Status: HE Approval 3/8/06 Project Manager: Paul MacCready
Drainage: Kenneth Crossman Subdivision Name: Panther Lake Ridge
Number of Lots: 32 Property size - Acres: 107.5
Crit Areas Ord: Non-Exempt-Rural Duplex Lots Proposed: No
Zoning - Existing: R-5 Zoning - Requested: R-5
Present Land Use: sfr Lot Sz Average Used: No
WR on Site: Yes 120 DAY CLOCK TOTAL: 164
120 DAY CLOCK ON?: Yes LAST UPDATED BY PROCESS?: 5975-PUBLIC-HEARING on 12/01/05
Description:
32 lot rural cluster
Conditions:
12-month preliminary approval extension approved to 3/8/2012. ed caine

Final approval by HE after all appeals exhausted was Oct 13, 2006
Preliminary plat approval extended to full 12 years per SCC. Pmac

Actions Related to Application Status Scheduled to End Date End Date
Preliminary Review
Application Requirements  Closed    4/20/2004  
Critical Area Study  Received    4/20/2004  
Prel Review Bio  Closed  4/30/2004   5/7/2004  
Prel Review Fire  Closed  5/11/2004   5/11/2004  
Prel Review Drainage  Denied  5/11/2004   5/14/2004  
Prel Review DPW  Disapproved  5/11/2004   5/18/2004  
Prel Review Bio  Disapproved  5/11/2004   5/24/2004  
Prel Review DOT  Approved  5/11/2004   6/8/2004  
Completeness
Inc-Appl Expiration Deadline  Open     
APPL SUBM ADDL INFO  Open     
APPL-ADDL INFO ADEQUATE  Open     
APPL DETERMINED COMPLETE  Complete  5/18/2004   5/18/2004  
COMP-ADDL INFO REQUESTED  Closed    5/24/2004  
Completeness Letter  Closed  5/18/2004   5/24/2004  
Comp-Appl Expiration Deadline  Closed  5/24/2005   7/6/2004  
COMP-ADDL INFO ADEQUATE  Closed    7/23/2004  
COMP-ADDL INFO REQUESTED  Closed    7/28/2004  
COMP-ADDL INFO ADEQUATE  Closed    9/3/2004  
Notice of Application
Public Comment Period  Open  5/19/2004    
Notice of Application  Closed    4/23/2003  
POSTING RECEIVED  Closed    4/22/2004  
Revision Review
Public Works Revision  Closed  7/19/2004   7/20/2004  
Bio Revision Review  Disapproved  7/19/2004   7/22/2004  
Fire Revision Review  Closed  7/19/2004   7/27/2004  
Drainage Revision  Denied  7/19/2004   7/27/2004  
Addl Info Adequacy Letter  Closed  7/23/2004   7/28/2004  
Public Works Revision  Disapproved  9/3/2004   9/2/2004  
Bio Revision Review  Disapproved  9/3/2004   9/7/2004  
Drainage Revision  Approved  9/3/2004   9/13/2004  
Addl Info Adequacy Letter  Closed  9/7/2004   9/21/2004  
Bio Revision Review  Approved  10/15/2004   10/14/2004  
Addl Info Adequacy Letter  Closed  10/19/2004   10/21/2004  
Bio Revision Review  Closed  3/14/2005   3/22/2005  
Bio Revision Review  Closed  4/22/2005   4/21/2005  
Addl Info Adequacy Letter  Closed  8/3/2005   8/30/2005  
TD/Hearing Process
Precondition Reminder Letter  Open     
Precondition Extension  Open     
Planner Precondition Review  Open     
DPW Precondition Review  Open     
Other Precondition Review  Open     
TD/HEARING POSTING VERIFICATION  Closed  9/30/2004   9/23/2004  
SEPA Appeal Period  Closed  10/4/2004   10/4/2004  
SEPA Comment Period  Closed  10/4/2004   10/4/2004  
Staff Rec/Appeal Response  Closed  10/27/2004   11/2/2004  
File to Hearing Examiner  Closed  11/2/2004   11/3/2004  
PUBLIC HEARING  Closed  11/9/2004   11/9/2004  
HEARING EXAMINER DECISION  Deny w/o Prejudice    1/26/2005  
Reconsideration Requested  Denied    5/26/2005  
File Received from Hearing Examiner  Closed    6/10/2005  
Staff Rec/Appeal Response  Closed  11/2/2005   11/4/2005  
TD/HEARING POSTING VERIFICATION  Closed  11/23/2005   11/23/2005  
File to Hearing Examiner  Closed  11/23/2005   11/23/2005  
PUBLIC HEARING  Closed  12/1/2005   12/1/2005  
HEARING EXAMINER DECISION  Approved    3/8/2006  
Staff Rec/Appeal Response  Closed  9/12/2006   9/12/2006  
SEPA Appeal Filed  Denied    2/28/2007  
Reconsideration Requested  Denied    2/28/2007  
Approvals
Extension of Prel Approval  Open     
Prel Approval Expiration Letter  Open     
Prel Approval Expires  Closed  3/8/2013    
Prel Approval Expires  Open  3/8/2013    
Prel Approval  Closed    3/8/2006  
1st Review-Engineering
1-Const Review-Fire  Approved  4/14/2006   4/12/2006  
1-Const Review-Bio  Disapproved  4/13/2006   4/13/2006  
1-Route Plans to DPW  Disapproved  4/21/2006   4/25/2006  
1-Route Plans to R/W  Closed    4/28/2006  
1-Route Plans to Reviewer  Disapproved  5/19/2006   5/12/2006  
1-Applicant/Engineer Notification  Closed    5/22/2006  
First Review  Closed  5/19/2006   5/22/2006  
2nd Review-Engineering
2-Const Review-Fire  Open     
Second Review  Approved     
2-Route Plans to R/W  Open     
2-Applicant/Engineer Notification  Open     
2-Const Review-Bio  Approved w/Corrections    12/26/2007  
2-Route Plans to DPW  Disapproved  1/14/2008   1/16/2008  
2-Route Plans to Reviewer  Disapproved    1/17/2008  
3rd Review-Engineering
Third Review  Open     
3-Route Plans to R/W  Open     
3-Applicant/Engineer Notification  Open     
3-Const Review-Fire  Open     
3-Const Review-Bio  Approved  3/24/2008   3/19/2008  
3-Route Plans to DPW  Approved  3/24/2008   3/20/2008  
3-Route Plans to Reviewer  Approved  3/24/2008   4/15/2008  
Approvals-Engineering
EDDS Deviation  Disapproved  2/7/2008   1/24/2008  
EDDS Deviation  Approved  2/7/2008   2/4/2008  
Approvals-As-Builts
As-Built Approval  Closed    12/19/2011  
Project Ended
Project Ended  Open     